TORONTO (Reuters) - TransAlta Corp.
The project's total capital cost is now expected to be C$170 million ($163.5 million), up from C$130 million.
The power company said it will build 32 turbines, up from the original 25 turbines, expanding the output at the New Brunswick-based project to 96 megawatts from 75 megawatts.
The project, subject to regulatory and environmental approval, is expected to begin in early 2008.
($1=$1.04 Canadian)
© Reuters Limited. All Rights Reserved.
Reproduction or redistribution of Reuters content, including framing or similar means, is expressly prohibited without the prior written consent of Reuters. Reuters shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.